Arlington County:
“The Arlington County Board could approve another round of
neighborhood improvement projects at its meeting this Saturday. Six projects
are slated to receive $3.5 million in funding in the fourth and final round of
appropriations from 2012′s $11 million Neighborhood Conservation Bond. The
projects are:
- Street improvements to the 5700 block of 2nd Street S. and the 100 block of S. Kensington Street in Glencarlyn. Cost: $724,042. Expected completion date: June 2016.
- A trail connector from the 4800 block of 7th Street S. to the W&OD trail in Barcroft. Cost: $135,317. Expected completion date: October 2015.
- Pedestrian safety improvements to 19th Road N. between Woodstock Street and Upton Street in Waverly Hills. Cost: $753,845. Expected completion date: May 2016.
- Street improvements to S. Lang Street between Arlington Ridge Road and 28th Street in Arlington Ridge. Cost: $713,003. Expected completion date: October 2015.
- Streetlights and trail improvements on N. Ohio Street between 22nd Street and Washington Blvd in Highland Park Overlee Knolls. Cost: $380,369. Expected completion date: July 2015.
- Park improvements to Woodlawn Park in Waycroft-Woodlawn. Cost: 795,000. Expected completion date: None given.
The projects were chosen based on a priority scale and
approved for recommendation by the NCAC in December.”
~Writes Arlington Now